Electrical Thermography for Commissioning and Handover in the UAE
New electrical installations can leave site with loose terminations, poorly made joints and unbalanced loads that no one has seen yet. A thermographic survey at commissioning finds them while the contractor is still on site and still responsible.
What a commissioning survey covers
- Main switchgear and switchboards
- Distribution boards and busbar runs
- Transformers
- Motor control centres and starters
- UPS and standby power equipment
- Chiller, pump and HVAC plant supplies
What we look for
- Loose or high-resistance terminations and joints
- Overloaded or unbalanced circuits
- Faulty or under-rated components
Why do it at handover
- Defects are raised while they can still be corrected by the installing contractor
- You get a documented thermal baseline for every critical panel
- Your future PPM surveys can be compared against that baseline
Load matters
Thermography needs current flowing through the equipment. We agree the load conditions with you before the visit, because lightly loaded equipment can hide a fault that appears once the building is occupied. Where full load is not available, the report states the load at the time of each scan.
Who this is for
Main contractors, MEP contractors, consultants and developers handing over new or refurbished buildings. Our thermographers are certified Level 2 and Level 3.
What you receive
A PDF report with radiometric thermal images, visible photos, temperature differentials, fault grading and recommended actions.
Download an example electrical thermography report
Book a commissioning survey
Call +971 4 560 7296 or use the contact form with your project, equipment list and handover date. After handover, keep the baseline working with annual electrical thermography PPM.